October 20, 2005 is one date which Group A telecom employees
working in BSNL and MTNL would like to forget. Around 1,300 employees were not
allowed to enter their offices as their rooms were locked. Even their vehicles
were withdrawn, causing them further inconvenience. The remaining 900 employees
would also have met the same fate had they not got a stay from different courts.
This incident raises a lot of questions to be answered by
secretary, DoT as he is spearheading the absorption process. First, why did
things come to such a situation where corporate offices of both BSNL and MTNL
were locked for these employees? Second, it raises question mark on the
absorption process followed by DoT as only 16 ITSA officers opted for absorption
and this is even less than one percent of the total base. The biggest question
that arises is that when consultation process was followed for Group B, C, and D
level employees why was it not followed in the case of Group A level employees.
The Chain of Events
Why 1,300 ITSA employees of BSNL/MTNL were ordered to join DoT without
caring for operational and financial health of these companies. The repatriation
order was only valid for those who had not obtained a stay from different
courts. On the evening of October 19, 2005, BSNL and MTNL CMDs issued relieving
orders to 1,300 officers through e-mail. The very next day, when these officers
entered their offices to their utter surprise their offices were locked and they
were not allowed to enter. This incident was humiliating for these officers as
they have been working in these organizations for a long time and have been
heading their respective departments.
On October 20, Indian Telecom Service Association (ITSA)
challenged the October 18 order in the Central Administrative Tribunal (CAT) at
Allahabad. On October 21, ITSA got status ante (i.e. to restore the same status
as that of 17th October, 2005). Despite receiving the CAT order, the DoT
Secretary took his own time and finally asked both the CMDs on November 2, 2005
to honour and implement all court judgements. On November 8, BSNL CMD took back
all issues and employees where allowed to rejoin whereas MTNL CMD did it only on
November 17, 2005.
So what was the net impact for BSNL and MTNL during this
duration? The corporate offices of both MTNL and BSNL were working without ITSA
officers in duty. Even BSNL offices in Rajasthan and Maharashtra were badly
affected whereas in other states, the attendance of ITSA officers was minimal.
Due to this, there was no movement in terms of commissioning and deployment
front on the ongoing projects. Even existing services were not running smoothly
and there were major hiccups as it was not ironed out in the absence of top and
middle level managers and technical staff in these organizations. Even new
projects where further delayed and the situation is likely to remain the same
till the time the absorption issue is sorted out in the best interest of the
employees.
|
A Loss
of Rs 2,124 cr: who is responsible? |
 |
BSNL
loses
MTNL loses
BSNL and MTNL loses |
Rs 1,684
crore
Rs 440 crore
Rs 2,124 crore |
 |
|
New Projects Delay
60 mn GSM Tender
Transmission Projects
Broadband Multiplay Tender
NT DTAX Tender
IP-Tax tender
CDR Billing & CRM tender
CDN tender
Interest on unutilized Capex
Investment of
Mobile Services
Fixed Line Services
Internet and Broadband Services |
Rs 600 crore
Rs 200 crore
Rs 120 crore
Rs 120 crore
Rs 22 crore
Rs 72 crore
Rs 30 crore
Rs 400 crore
Rs 26,000 crore
Rs 100 crore
Rs 10 crore
Rs 10 crore |
Loss in Revenue for BSNL and MTNL
According to SS Sirohi, president, ITSA, "The absorption issue has
resulted in a total loss of around Rs 2,124 crore to BSNL and MTNL. This is a
direct loss but if one takes into account indirect losses, the total value comes
around Rs 3,000 crore." And continuation of this uncertainty will lead to
further losses, added Sirohi.
According to ITSA, BSNL's loss is estimated in the range of
around Rs 1,684 crore whereas MTNL's loss is estimated to be in the range of
around Rs 440 crore. In BSNL, there was loss on mobile front due to delay in
ongoing projects Even loss is expected in fixed line services, Internet services
and broadband services.
On the mobile front, there were a lot of problems in terms of
network rollout and commissioning. In the east zone, 3 mn lines commissioning
was due on Ocotober 10, 2005 but it is still pending. In the west zone, 3 mn
rollouts were to commence on October 2005 but now it has been rescheduled to
December 2005 . In the south zone, 4 mn were to be commissioned on August 17,
2005 by the Communications Minister but there was a negligible rollout.
On the broadband front there has been a drop in number of
connections from around 4,000 customers additions per day, it is now at around
2,500 customers per day. Even corporate leased line customers had to face the
wrath of network outages and they had no other option but to opt for back up
redundancies through private operators resulting in loss of revenue as well as
credibility for both BSNL and MTNL.
There was massive loss due to delay in new projects and this
is estimated by ITSA in the tune of around Rs 1,584 crore. All the mega plans of
BSNL have come to a standstill like: 60 mn GSM tender, one of the largest
tenders in the world which will help BSNL occupy the number one slot. The delay
in processing of BSNL's 60 mn tender will lead to a loss of around Rs 600
crores. Other projects which have been affected due to employee unrest are
transmission project, broadband multi-play tender, NT DTAX tender, IP-Tax
tender, CDR billing and CRM tender, CDN tender, and interest on utilized capex
investment of Rs 26,000 crore. All this comes to a cumulative loss of around Rs
1,564 crore.
In the case of MTNL, business losses were noted in the case
of GSM, broadband services, CDMA and virtual calling cards. 4 mn GSM targeted
for October 2005 shifted to December 2005. 2 mn broadband/CDN tender opening has
postponed indefinitely. Around 400,000 each CDMA lines in Delhi and Mumbai
targeted for October 2005 has been indefinitely delayed.
The overall loss in revenues for BSNL and MTNL is
irreparable. Apart from the losses, the faith of corporate customers took a
beating and this will take time as it is not easy, in view of the aggressiveness
of the private telecom players in the country. Apart from this, the overall
employee will take a beating due to one month drama titled 'DoT absorption
process.'
Why Change in Approach?
It is a big irony that the Minister and the Secretary had been talking about
the merger initially and synergy later for BSNL and MTNL without talking about
absorption of ITSA officers as it is a far bigger issue. As any merger or
synergy cannot happen without the completion of the absorption process.
It is very difficult to digest why DoT was in such a great
hurry to implement the absorption process before October 1, 2005 when it had
full five years to initiate absorption process even for Group A officers. It
seems from last five years there was no meeting on absorption. And the first
meeting between ITSA and DoT happened only on on 10th September 2005 that to on
a written intervention of Shakeel Ahmed, minister of state, government of India.
It is also an irony that when consultative process was
applied for Group B, C, and D employees. Why similar consultative process was
not conducted for Group A employees and why was the process started so late.
The absorption process for Group C&D employees was
finalized in 2002 where government offered attractive terms and conditions. In
this process, around 350,000 employees were absorbed in 2002. Even in case of
Group B employees absorption attractive terms and conditions was offered with
protracted negotiations over 2 years. And in this level around around 45,000
employees were absorbed. Out of this, around 3,000 employees in Group B, C, and
D have still not opted for absorption and still deemed on deputation.
|
ITSA
demands on absorption issue |
|
|
Parameters |
Demands |
DoT Response |
|

|
Similar pay scales and
service conditions in BSNL/MTNL |
HAG (E9+) and SAG (E9)
are same in both BSNL/MTNL. Therefore, the logic of giving different pay
scales at lower levels (NFSG, JAG) due to pension liability of government
in the case of BSNL but not so in the case of MTNL, does not hold good |
No assurance. |
|
Continuity in pay scales
from E9 to downwards for the officers |
The demand is natural as
the pay scales should follow sequential grades. There is an apprehension
that vacant IDA pay scales in the PSUs may be used at a later stage for
lateral entry and will invite litigation on the matter of superiority and
promotions, indication of which already exists in MTNL. |
No assurance. |
|
Special Allowance (SA) of
50 percent as per the model already agreed |
Model already agreed vide
CMD BSNL letter dated 26-09-2005 based on communication from Secretary,
Telecom should be implemented. This proposition will provide a justifiable
@38% rise as on 01-10-2005, after adjustment of losses due to HRA/perquisite
tax. The proposed increase in salary in still lower than the increase
provided to other cadres absorbed in these PSUs. However, the SA should be
outside the limit of 50 percent ceiling of perks and allowances set by DPE
guidelines. |
25 percent agreed. |
|
Ad-hoc payment already
made for working in PSU should not be recovered. |
This payment has been
made for doing works done in PSU environment. There is no logic for
recovery. Moreover it was never linked with absorption, while being
sanctioned. |
If small group is
absorbed in DoT then it would not be recovered otherwise it will be
recovered. |
|
|
|

|
Promotion Policy has not
been framed so far. Time bound functional promotions should be given up to
E9 (STS-4 yrs, JAG-9 yrs, NFSG-13 yrs, SAG-17 yrs). Time bound financial
up gradation every 5 yrs from E9 onwards with functional up gradation
depending upon availability of posts. The number of years for purpose of
promotions to be counted from 1st January following the year UPSC exam. |
The demand for time bound
promotion up to SAG (E9) level is as per the prevailing situation in Govt.
The HAG promotion to be given in 4-6 yrs after SAG. As the remaining
service after HAG shall be about 10-12 years, there is a need to have at
least one additional promotion above HAG to be given in 4-6 years time.
The scale should be given every year. |
Get absorbed and then we
will decide. |
|
No lateral entry for the
functions currently being handled by ITS officers |
There is no requirements
for lateral entry as ITS officers are well experienced and qualified to
handle the currently allotted jobs/functions. Lateral entry will affect
the aspirations and promotion avenues. |
Not agreed. |
|
Reservation of board
level posts for ITS officers |
ITS officers could aspire
for the posts up to members of Telecom Commission (Secretary level) while
being in governement. In order to meet the legitimate career aspirations
and for professional management of MTNL/BSNL, these posts should be
reserved for ITS (absorbers/non-absorbees) officers. ITS have been holding
these posts so far and we are only asking for protection of existing
career progression. The current eligibility criterion for selection makes
these posts open to outside applicants also. Incumbent CMD (RSP Sinha) and
Director (B Shivkumar) – HRD in MTNL are current examples of entry of
non-ITS. Therefore, the postings should be done by a search committee in
DoT, as was being done for MTNL for many years. Government has powers to
exempt any PSU from the purview of PESB any time. |
Not agreed. |
|
Option should be continue
in DoT rather than for government service. Allocating and en-cadreing
various ex-cadre posts. Presently handled posts/functions should remain
en-cadred. |
In order to meet
promotional aspirations of non-optees, all the en-cadred posts as on
01-10-2000 shall remain en-cadred to ITS. Efforts may also be made to
en-cadre various telecom related posts in other ministries.
|
100 employees will be
accomodated and rest will be kept in surplus.
|
|
|
|

|
Modifications in 37 A to
ensure payment of pension and medical benefits from Government funds for
the service rendered up to the date of dis-investment beyond 51%. |
Suitable modifications
may be done in Rule 37 A (para 25) to ensure payment of pension beyond 51%
disinvestments of government equity. 5 years benefits in service shall be
given in qualifying service and pension paid accordingly. Government
should modify the gazette to address this demand. Government guarantee
about extension of medical benefits should also be provided in respect of
previously retired employees and serving up to the date of such
disinvestments. |
No modification in rule
but a leeter will be given.
|
|
Pro-rate pension to be
paid under the rule 37 (to be paid by the government) from prospective
date. Suitable compensation to the officers who have rendered less than 10
years of service. Medical benefits to be ensured after retirement. |
The pro-rata pension
should be paid from the prospective date of account for the full service
rendered by the officers in the government. Provision of pro-rata pension
on the retrospective date is loss of qualifying service by 5 years, which
is bad in law. The inter-se seniority shall, however, be maintained. |
No modification in rule
but a leeter will be given. |
But the same exercise was not followed by DoT in case of
Group A employees. When BSNL was corporatized on October 1, 2000 every employee
was given a formation memo, which said all employees will be given permanent
absorption in these PSUs after finalizing suitable terms and conditions. So,
instead of finalizing suitable terms and conditions with inbuilt protection of
current service conditions, the government moved in a hasty manner and
unilaterally decided to dictate certain terms and conditions for absorption in
PSUs without giving any opportunity to Group A officers for dialogue or
negotiation despite persistent request with DoT Secretary and Minister of
Communications.
|
About
ITSA
ITSA is an association of Group A central civil services employee working
in the Department of Telecomunications (DoT), BSNL, MTNL, and TCIL. The
employees work in these companies as director, DDG, senior DDG, joint DDG,
advisor, member, DGM, GM, CGM, and executive director. They work in
different departments like policy formulation, planning, deployment,
marketing, and commercial.
The absorption process has affected
around 2,200 Group A employees of which around 1,800 work in BSNL, 250 in
MTNL, and 150 in DoT and TCIL. |
The Demands
On February 2, 2005, the government got the cabinet approval for the terms
and conditions for absorption of Group A officers in BSNL and MTNL without
consulting them and it was done in a secretive manner. These conditions were
found to be degraded and demeaning and full of ambiguity. It was noticed that
there was loss of payment in terms of emoluments and degradation of promotional
avenues in the government.
For those who join BSNL and MTNL, the three main demands are
pay and emoluments, promotional avenues and career progression, and security of
pension/continuity of government pension, says SS Sirohi.
For those who opt for government, they should be deployed
gainfully in DoT for all existing telecom functions that they have been
discharging. In case they are not absorbed with DoT, they should be accomodated
in other ministries for telecom related functions after adjusting these offices
against such posts. And the remaining officers should be gainfully utilized by
temporarily keeping them on deputation to these PSUs keeping their service
condition intact until the government is able to redeploy them.
About their next course of action, Satish Sharma, general
secretary said, "We are not going to sign inferior conditions and we are
not following the path of agitation as it causes inconvenience to common
man."
Conclusion
Recently BSNL announced FY 2004-05 results and it was encouraging both in
terms of revenue as well as profits. Even the company is giving a tough fight to
private players on the mobile front. So, why is government bent on creating
hurdles for the company thereby creating problems in its working. Is it not a
deliberate move to bring down the valuation of BSNL and MTNL so that it can be
sold at a lower level whenever the government plans to do it in future? Is it
not a deliberate move to help private operators increase their market share by
delaying expansion projects, which takes a lot of time in BSNL and MTNL? Is it
not a deliberate move to lower morale of ITS officers so that a way is created
for IAS officers in the top positions whether in the circle level or corporate
level in terms of policy formulation.
All these issues have to be thrashed out in the well being of
BSNL and MTNL. Any further delay in the absorption process will be detrimental
for all parties involved in the process. The ill feeling of employees cannot be
erased easily and so consultative process will come to rescue with the formation
of high powered committee with representations from Group A officers in a time
bound manner so that everybody benefits including Group A employees, BSNL, MTNL,
DoT, and public at large. Any wrong move can kill public giants BSNL and MTNL
and it would not be good for the Indian economy.
Pravin Prashant
Page(s) 1